Mayor's Action Plan for Safer Streets Across Atlanta
What’s the status of the corridor projects in Mayor Keisha Lance Bottoms’ 2019 Action Plan for Safer Streets Across Atlanta? Find out using our interactive online infrastructure project tracker! Click the arrows at the top left of the map to view the legend and toggle layers on and off. Or, visit the Infrastructure Project Tracker StoryMap for an interactive narrative experience.
Completed as of most recent update 6/15/22:
6 projects
11.75 miles — including 6.59 miles of bike/LIT lanes, of which less than 1 mile are protected bike lanes
Background
Mayor’s Action Plan for Safer Streets Across Atlanta
On September 25, 2019, in response to several fatal scooter crashes, Atlanta Mayor Keisha Lance Bottoms announced the Action Plan for Safer Streets Across Atlanta, a two-year $5-million plan promising to "change our streets by creating safer, dedicated spaces for cyclists and scooter riders." The Plan aimed to "establish new connections between key neighborhoods across the city" and bring "more than 20 miles of safer streets" through accelerated safety improvements and redesigns across 26 Atlanta corridors. According to the Plan, funding would come from “redesigning existing projects, departmental budgets, and community partners.”
Bike/scooter network
By the end of 2020, Mayor Bottoms pledged to double Atlanta's on-street protected bike network from 4 to 8 miles, and to triple it to at least a 12-mile network of protected bike lanes by the end of 2021. Our research found that ATLDOT and partner agencies have completed around 11 miles of the Mayor’s Action Plan for Safer Streets’ projected 20+ miles of safer streets to date. Of those, about 6.6 miles were bicycle/LIT lanes or multi-use trails. Less than a mile was protected bike lanes.
High-Injury Network
Six of the Plan's 22 target corridors are part of Atlanta's High-Injury Network (HIN), which includes the city's most dangerous routes for walking and biking. Ralph David Abernathy Boulevard, Lee Street, Martin Luther King Jr. Drive, and Campbellton Road, as well as Cascade Avenue and DeKalb Avenue — two significant corridors we advocated for — are included in the mayor's plan.
Despite our call for the City to use the mayor’s plan as an opportunity to prioritize corridors on the High-Injury Network, the Martin Luther King Jr. Drive Improvement Program is the only completed project within the HIN to date. The five remaining streets are currently in the planning and development or design phases of completion. More specifically, the Lee Street project is still in the planning & development stage, while the projects for Campbellton Road, Cascade Road and Avenue, and Ralph David Abernathy Boulevard are in the design phase.
Prioritizing projects on the High-Injury Network is critical because of the high risk that more people could be injured or killed on these dangerous streets. For instance, as recently as Wednesday, August 25, 2021, a woman lost her life on Cascade Road while driving.
Cycle Atlanta and Quick Implementation Bicycle Projects
The Mayor's Action Plan for Safer Streets includes several projects from 2017’s "quick-build" bicycle projects identified in Cycle Atlanta 2.0, including Brady Avenue, Central Park Place, Courtland Street, Gilmer Street, Peachtree Street, Porter Place, and Whitehall Street.
Action Plan for Safer Streets targeted corridor projects
In 2021, the Atlanta Department of Transportation (ATLDOT) published an interactive Project Map that allows the public to track the progress of ongoing infrastructure projects across the city.
This is a welcome step forward. However, while ATLDOT's map shows many of the Action Plan for Safer Streets' target corridors, some are missing or have minimal information, making the entire target network appear shortened.
Based on the available information on ATLDOT's interactive map, five out of 34 of the plan's target projects are complete, while the majority of the targeted routes are still in the design phase, construction phase, or have limited information available. Using our infrastructure project tracker, we found that the Atlanta Department of Transportation (ATLDOT) and partner agencies have completed 11.75 of the 20 pledged miles between 2019-2021.
During the City’s infrastructure program meetings in November 2021, we learned that several of these projects are included in the proposed bond and TSPLOST lists that will go to voters for approval in May 2022. While we don't know how mayor-elect Andre Dickens' administration will handle these projects, we're excited to continue keeping track of them.
Based on our research, the current stages of completion for each project in the Mayor's Action Plan for Safer Streets Across Atlanta are listed below.
Project completion phases
Not Started or Limited Information Available:
- Georgia Avenue (TSPLOST 2022)
- McDaniel Street (TSPLOST 2022)
- Oakland Drive
- Pryor Street (TSPLOST 2022)
Planning and Development:
- Lee Street (barricades were placed along West End MARTA station as an interim solution)
Design Phase:
- Campbellton Road Complete Street and Campbellton Road Pedestrian Improvements
- Cascade Road Complete Street Phase 2 (Avon Avenue to Ralph David Abernathy Boulevard)
- Central Park Place Design
- Courtland Bicycle Mobility Improvements
- Cycle Atlanta 1.0 Bicycle Mobility Improvements
- DeKalb Avenue Complete Street Phase 2
- Gilmer Street Bicycle Mobility Improvements
- Jesse Hill Drive Design
- Ralph McGill Boulevard Bicycle Mobility Improvements (east of Courtland Street)
- Washington Street Bicycle Mobility Improvements
Funding, Permitting, or Procurement:
- Piedmont Avenue: Pedestrian Safety
- Piedmont Avenue: Complete Street (permitting is underway)
- Juniper Street Complete Street (permitting is underway)
- Ralph David Abernathy Boulevard Complete Street
- Whitehall Street Design
Construction Phase (10.4 miles):
- Cherokee Avenue Safer Streets - starting in November 2021 (barricades placed as interim protection for lane)
- Cascade Road Complete Street Phase 1 (from Atlanta City limits to Willis Mill Road and from Delowe Drive to Avon Avenue) - groundbreaking ceremony in November 2021
- DeKalb Ave Safety Improvements Phase 1 - started in December 2021 (from Hurt Street to Elmira Place)
- Spring Street Complete Street Quick Build LIT Lanes - started in October 2021 (from 3rd Street extended to 17th Street; Phase 2 construction forthcoming)
- West Peachtree Street Complete Street Quick Build LIT Lanes - started in October 2021 (from Linden Avenue extended to 17th Street; Phase 2 construction forthcoming)
- BeltLine Westside Trail Segment 3 (Marietta Boulevard) - started in March 2021
Complete (11.75 miles, of which 6.59 are bike lanes or multi-use trails):
- Anderson Avenue Sidewalk: 0.78 miles of sidewalk
- Bill Kennedy Way: 0.47 miles of protected bike lane
- Brady Avenue: 0.45 miles of protected bike lane
- Martin Luther King Jr. Drive Complete Street: 2.67 miles of standard bike lane, including 0.61 miles of multi-use trail along the Westview Cemetery
- Joseph E Boone Boulevard Complete Street: 1.21 miles of of standard bike lane (with some interruptions at intersections)
- BeltLine Westside Connector Trail: 1.79 miles of multi-use trail
Next steps
Atlantans deserve safer streets. Although COVID-19 set back projects all over the country, we will continue to hold government agencies accountable for building what is planned and sharing timely updates with the public when plans change.
Stay tuned for opportunities to take action to advocate for these projects.